Testata della pagina

Gronda di Genova

A strategic work for our Country, an international engineering challenge

The Gronda di Genova project is accompanied by the Environmental Monitoring Plan, developed according to the Guidelines of the Ministry of the Environment, the indications emerged within the Environmental Impact Assessment procedure and the observations expressed by the Agenzia Regionale Protezione Ambientale della Liguria (ARPAL).

This plan is considered integrated because it aligns with the EIA Decree, which emphasizes the general principle of integrating specific environmental monitoring activities with the activities conducted by ARPA Liguria. This integration is aimed at supporting the competent Public Bodies and leveraging potential synergies.

The Environmental Monitoring Plan aims to conduct environmental monitoring activities in the area to evaluate the impact of the motorway construction before it becomes operational, as well as the effectiveness of any mitigation efforts.

Piano di monitoraggio ambientale

All environmental components are considered in the environmental monitoring plan:

SURFACE WATERS
Detection methods

The construction work involving bridges, viaducts, and river crossings, as well as activities in the riverbed such as riverbank systems, temporary fords, and widening of piers and abutments, require special attention to monitoring and controlling watercourses. This includes assessing the quality and quantity of water and the health of river ecosystems. As part of the Environmental Monitoring Plan, we have included a specific component called "Surface Waters and River Ecosystems" to address these aspects.

Method A1

Quantitative measurements, i.e. current flow measurement using a Doppler-type instrument;

Method A2

Qualitative measurements - chemical-physical parameters (air temperature, water temperature, pH, conductivity, dissolved oxygen);

Method A3

Qualitative measurements - chemical parameters (TSS - Total Suspended Solids, COD, Total Hydrocarbons, PAHs, Total Surfactants, Aluminium, Total Chromium, Nickel, Zinc, Cadmium, Lead, Calcium, Chlorides, Sulphates).

Method A4

Quality measurements - chemical and microbiological parameters (Nitrates, Nitrites, Ammonia, BOD5, Escherichia Coli).

Method A6

Misure qualitative – parametri biologici (MHP Multi Habitat Proporzionale)

Method A7

Hydromorphological measurements (river function index IFF)

Correntometro doppler
Campionamenti di acque superficiali
Equipment used
Doppler Current meter

Doppler current meter flow measurement quantifies the extent of outflows, providing data that can be related to the hydrological regime of the watercourse as well as the chemical and physical parameters of water quality, to assess the extent of pollutant loads flowing into the control section. During the measurements, the flow rate will be measured using current measurements. These measurements are usually carried out with Doppler Equipment (Doppler current meter). It is planned to perform flow rate measurements on all 41 river sections included in the Environmental Monitoring Plan, which are located in the area subject to intervention.

Surface water sampling

Sampling for chemical, microbiological, biological, or hydromorphological measurements on 22 river sections affected by the works and included in the Environmental Monitoring Plan has been planned.

A total of 41 river sections were included in the Environmental Monitoring Plan, of which

19 sections concern surface water bodies subject to potential interference of a quantitative nature due to the excavation of the tunnels: Measure A1 is planned for these sections

22 sections concern surface water bodies subject to potential qualitative and quantitative interference linked to the construction site: In these sections, a site-specific combination of analytical sets A1/A2/A3/A4/A5/A6/A7 is planned.

GROUNDWATER
Detection methods

The presence of important underground works in the project, capable of altering the underground water flow regime, together with a hydrogeological criticality due to the interference of these works with the present aquifer, requires the inclusion of the Underground Water component in the Environmental Monitoring Plan.

Method B1

Quantitative measurements, i.e. piezometric level on wells and piezometers, volumetric flow rate on springs or water flows in tunnels;

Method B2

Quality measurements - chemical-physical parameters (turbidity, temperature, pH, conductivity, dissolved oxygen, Redox Potential);

Method B3

Quality measurements - chemical parameters (Bicarbonate, Calcium, Magnesium, Potassium, Sodium, Sulphates, Chlorides, Nitrates, Silica).

Method B4

Qualitative measurements - microbiological parameters (E. coli).

Method B5

Qualitative measurements - chemical and microbiological parameters on water drained from the tunnels (Aluminium, Chromium, Chromium VI Iron, Manganese, Copper, Nitrates, Bicarbonate, Calcium, Sodium, Magnesium, Potassium, Sulphates, Chlorides, Total hydrocarbons)

Campionamenti di acque sotterranee
Tools used
Continuous control units

The Chemical and Physical parameters continuously monitored by the probe are water temperature and volume flow rate.

It is planned to install about 15 continuous monitoring stations, during the construction phase, on as many groundwater wells located in the area under intervention among those with the highest risk of interference.

Groundwater sampling

Groundwater sampling is planned for 161 sites

MARINE WATER ENVIRONMENT
Detection methods

The presence in the Maritime Work made it necessary to include the Marine Water component in the Environmental Monitoring Plan.

Method A1-M

Continuous current meter in the Calma Canal measures current speed and direction;

Method A2-M

Continuous monitoring of chemical and physical parameters (turbidity, temperature, pH, conductivity, dissolved oxygen) through the installation of three multi-parameter probes;

Method A3-M

Quarterly monitoring of marine waters at no. 3 sampling sites (Total Suspended Solids; Total Hydrocarbons; PAHs; Total PCBs; Anionic Surfactants; Non-Ionic Surfactants; Total Surfactants; Total Chromium; Nickel; Zinc; Cadmium; Lead; Mercury; Arsenic; Copper; Selenium; Iron).

Method A4-M

Six-monthly monitoring of marine sediments at no. 4 sampling sites (Total Hydrocarbons C>12; PAHs; Total PCBs; Granulometry; Total Chromium; Nickel; Zinc; Cadmium; Lead; Mercury; Arsenic; Copper; Selenium; Iron).

Method A6-M

Quality measurements - chemical and microbiological parameters (Nitrates, Nitrites, Ammonia, BOD5, Escherichia Coli).

Method A7-M

Qualitative measurements - biological parameters (MHP Multi Habitat Proportional)

Method A8-M

Hydromorphological measurements (river function index IFF)

Strumentazione utilizzata
Strumentazione utilizzata
Tools used
Continuous multi-parameter probes

Some of the chemical and physical parameters continuously monitored by the probe are temperature, pH, turbidity, etc. Three measuring points are planned along the Calma Canal in an eastern, central and western position, the micro-location of which will be agreed with the Control Authority

Current Meter

The purpose of installing a current meter is to continuously measure the direction and speed parameters of the current over the entire water column and, consequently, to allow assessments of the current generated by the wave motion incident upon the airport stretch of water. It is planned to install a current meter at 1 site located in the centre of the Calma Canal

Marine water sampling

Water samples will be collected at known depths using Niskin-type bottles positioned in the middle of the water column. For marine sediment sampling, a bucket capable of collecting a minimum volume of 5 liters of sediment will be used.

There are 4 planned measuring points: 3 along the Calma Canal in eastern, central, and western positions, and 1 at the mouth of the Varenna stream. The specific location for the Varenna stream measurement will be agreed upon with the Control Authority.

ATMOSPHERE
Detection methods
Method A2 Air Sampler

Method A2: Measurement of total suspended dust (PTS) and PM10 particulate matter for 15 days in the vicinity of construction sites;

Method A2Bis Air Sampler

Method A2bis: Survey of asbestos fibres with sequential sampler

Method A3 Fixed control unit

Method A3: Continuous measurement with fixed air quality monitoring unit.

Ante, course and post measurements are carried at a series of localised points by using reference methods, quarterly for the a2 method and continuously with the a3 method.
Centralina controllo qualità aria
Equipment used
Air quality control unit

The control unit continuously monitors a set of chemical and meteorological parameters, such as nitrogen, carbon monoxide, wind, and precipitation.
One measurement point is planned, and its location will be agreed upon with the Control Authority. For dust monitoring, the unit tracks total suspended particles, PM10, and asbestos fibers. Twelve measurement points are planned, and they will be located throughout the area covered by the intervention.

VIBRATIONS
Detection methods
Method V1

Short-term measures aimed at reducing discomfort to people;

Method V2

Short-term measures aimed at mitigating structural damage.

Analizzatore in tempo reale
Equipment used
Real-time analyser

8-channel Sound Level Meter Integrator, Recorder and Real Time Analyzer for noise and vibration measurement, analysis, and monitoring. This tool can measure parameters. There are 14 measurement points located in the intervention area.

NOISE
Detection methods
Method R2

24-hour measurements, semi-fixed partially manned workstations, to survey site activities

Method R3

7-day measurements, unmanned fixed stations, for vehicle traffic surveys;

Method R4

Short-term measurements in the living environment to verify the differential limit;

Method R4BIS

Short-term measures in the living environment to verify direct mitigation interventions on receptors.

fonometro integratore
Equipment used

The equipment used to assess noise pollution is an integrating sound level meter. It can measure a very large number of parameters. It is planned to have 32 measuring points spread over the area covered by the intervention.

VEGETATION
Detection methods

The potential impact on vegetation from the construction and operation phases of the motorway upgrade will be determined using the following monitoring methodologies:

Phytosociological values

A phytosociological survey essentially consists of describing the vegetation based on the plant species that constitute it, specifying the composition and structure of the plant stand also by defining the quantitative relationships between individual species

Surveying the vegetation value of riverbeds

The survey takes place both through the use of vegetation maps and field trips, and leads to the subdivision of the watercourse into homogenous vegetation sections.

Monitoring inspection

For each monitoring site of the vegetation component, an inspection is conducted in the area adjacent to the worksite, in order to check and note on special control sheets the general aspects of the impacted area, and in particular the general state of the habitat, the morphological alterations of the area, the presence of foreign material or invasive species, etc.

operatori esperti in botanica
Equipment used

For the monitoring of the vegetation component, specific equipment is not foreseen; the surveys will be carried out by botanical experts. Twenty-three monitoring sites are expected to be located on the area covered by the intervention.

FAUNA
Detection methods

Monitoring is based on the analysis of the zoological groups that are indicated in the Environmental Impact Study as being most exposed to disturbance from works.
The groups proposed for monitoring are listed below:

Birds

The surveys will be aimed at the qualitative definition of the community present and the observation of changes in the population.

Crayfish

Observations are to be carried out along the river shaft, from the mouth of the watercourse to an area upstream of the impacted area.

Amphibians

The surveys will be aimed at the qualitative definition of the community present, with quantitative data collection on the species and the evolution of the populations during work interference.

Troglofauna monitoring

These organisms are closely related to the cave environment, and adapted to living in the dark, in an unventilated atmosphere, with high humidity and a quite constant temperature.

operatori specializzati
Equipment used

For the monitoring of the Fauna component, the use of specific equipment is not foreseen; the surveys will be carried out by highly specialised operators for each fauna group investigated.

Twelve monitoring sites are planned to be located in the area covered by the intervention.

PHYSICAL LAYOUT OF THE TERRITORY
Detection methods

The monitoring methods take into account the geological and geomorphological conditions of the areas impacted by the construction, as well as the mechanical properties of the rock formations and the factors influencing the movement of landslides identified and studied during the design phase. These methods are designed to offer guidance for observing and analysing ongoing phenomena, and to gather data for developing mitigation measures and assessing the effectiveness of planned or ongoing consolidation and stabilization efforts.

The following methods are widely used in geotechnical monitoring of the land. They are used to evaluate fluctuations in groundwater levels, monitor landslide movements, and identify sliding surfaces. These two activities are considered complementary, so inclinometer measurements are often used alongside groundwater level monitoring at most sites.

Freatimetro
Equipment used
Phreatimeter

This tool can measure the static piezometric level and the groundwater level from ground level. There are 29 measuring points located throughout the area covered by the intervention.

Inclinometer system

This tool can measure the extent and speed of movement. A total of 29 measuring points is planned throughout the area covered by the intervention.

With regard to the atmosphere component, considering the presence of natural asbestos in some of the formations affected by the excavations, asbestos monitoring is planned as part of the activities of the environmental monitoring plan shared with Arpa Liguria.

In detail, the integrated environmental monitoring plan has the following objectives:

analizzare le condizioni ante operam

analyse ante operam conditions in order to understand existing environmental dynamics;

garantire il controllo di situazioni specifiche

ensure the control of specific situations, so that work can be adapted to particular environmental and social needs;

verificare le interferenze ambientali

verify the environmental interferences that may occur as a result of the construction of the work, distinguishing them from the alterations induced by other natural factors or those linked to human activities in the area unrelated to the motorway works;

segnalare il manifestarsi di eventuali emergenze

report the occurrence of any emergencies in order to prevent the development of events compromising the environmental quality of the area;

verificare l’efficacia dei provvedimenti adottati

verify the effectiveness of measures taken to mitigate any impacts induced by the motorway works;

controllare la fase di entrata in esercizio delle opere

control the commissioning phase of the works.

The main purpose of the monitoring plan is to share information about the quality of the different components being monitored with the local area. This is done to prevent any environmental issues from arising. When precautionary limit values are reached, the plan calls for the implementation of corrective actions to ensure that environmental regulations are always adhered to.

To ensure the accurate assessment of the impact of motorway construction on the environment, particularly the effectiveness of the included mitigation measures, the environmental monitoring plan will be conducted in three distinct phases.:

1
ante operam

prior to the commencement of works lasting at least 12 months, to verify the environmental state of the sites in their current condition not yet affected by construction activities;

2
work in progress

which accompanies the duration of works, which is estimated to be about 10 years, necessary to carry out environmental monitoring on the territory and assess the effects of the construction;

3
post operam

following the completion of the works, lasting 12 to 24 months depending on the environmental components examined, to verify compliance with the limits set by the regulations and to take action on the optimisation of the planned mitigation works.

il rilievo dei dati ambientali

For the environmental survey, we will use standardized methods for each component to ensure compliance with regulations and consistent results. In addition to mobile instruments used by our technician teams, there will also be fixed instruments in place.

CONSULT THE FINAL DRAFT OF THE ENVIRONMENTAL MONITORING PLAN

SEE THE 2018 QUARTERLY REPORTS

SEE THE 2019 QUARTERLY REPORTS