New improvement works of the motorway network

|

|
The works in progress
Below is a list of the improvement works by Autostrade per l'Italia as provided for in the Agreement with ANAS of 1997 and in the IV "Atto Aggiuntivo" of 2002 effective from June 2004, and its Subsidiaries. In addition to the construction of third and fourth lanes, provision is made for creating new exit junctions and the building and modification of the facilities of lighting, ventilation and fire-prevention systems of 466 tunnels of the network. The figures given below do not include other investments, necessary for making structural and technological improvements to the network, amounting to approximately €900 million.
| WORKS INCLUDED IN THE AGREEMENT OF 1997 |
Extension Km |
*Amount € mil. |
 |
A1 |
4th lane MODENA - BOLOGNA |
31,6 |
1881 |
 |
A1 |
3rd lane CASALECCHIO - SASSO MARCONI |
4,1 |
59 |
 |
A1 |
VARIANTE DI VALICO |
62,5 |
3.1772 |
 |
A1 |
3rd lane BARBERINO - INCISA |
58,5 |
1.463 |
 |
A1 |
3rd lane ORTE - ROMA NORD |
37,8 |
188 |
 |
A8 |
3rd and 4th lanes MILANO - GALLARATE |
28,7 |
65 |
 |
A14 |
3rd lane BOLOGNA B.GO PANIGALE - SAN LAZZARO |
13,7 |
2033 |
| |
|
OTHER WORKS |
|
25 |
| Total |
|
|
236,9 |
5.370 |
| WORKS INCLUDED IN THE IV ADDITIONAL DOCUMENT OF 2004 |
Extension Km |
*Amount € mil. |
 |
A1 |
3rd lane ROMA NORD - G.R.A. |
18,7 |
1584 |
 |
A4 |
4th lane MILANO EST - BERGAMO |
33,6 |
514 |
 |
A8 |
link to NUOVA FIERA DI MILANO (Milan's new trade fair district) |
3,8 |
85 |
 |
A9 |
3rd lane LAINATE - COMO GRANDATE |
23,2 |
186 |
 |
A14 |
3rd lane RIMINI NORD - PEDASO |
171 |
2.491 |
 |
A7-A10 |
GENOVA BYPASS |
34,8 |
1.8005 |
| |
|
OTHER WORKS |
|
229 |
| Total |
|
|
285,1 |
5.463 |
| TOTAL WORKS AUTOSTRADE PER L'ITALIA (A) |
522,0 |
10.833 |
| TOTAL WORKS BY SUBSIDIARIES (B) |
52,2 |
1,201 |
| TOTAL WORKS (A+B) |
574,2 |
12.034 |
| * |
The figures are updated at 31.10.2007 and are subject to variation during Authorisation- and Works periods. |
| 1 |
Of which the sum of 180 million € is provided for in the plan for 1997 and 8 million € in other investments. |
|
2
|
Of which the sum of 3,170 million € is provided for in the plan of 1997 and 7 million € in other investments.
|
| 3 |
Of which the sum of 59 million € is provided for in the plan of 1997 and 144 million € in other investments. |
|
4
|
The sum refers only to the Fiano-Settebagni section pending definition of the Settebagni-GRA section.
|
|
5
|
Provisional figure as preliminary project design is currently undergoing definition.
|

|